Project Details

  • Construction Date

    31/08/2015

  • Location

    Thai Nguyen

  • Construction Investor

    Thai Trung Steel Rolling Joint Stock Company

  • Value

    340 bill 483 m + 15.5 mil Euro

  • Categories:

Project Description

This project has the capacity up to 500.000 tons/ year and the total capital of over 1.300 billion VND.

On 16 July 2009, the groundbreaking ceremony of Steel Rolling Mill Plant with capacity up to 500.000 tons/year was officially taken place at Thai Nguyen Iron and Steel Complex.

On 13 June, Bank for Investment and Development of Vietnam (BIDV), Vietcombank, Bank for Agriculture & Rural Development (Agribank) and Thai Trung Steel JSC signed “Credit Sponsor Contract”.

Due to this, the plant needs the total estimated investment capital of more than VND 1,300 billion.

The plant is expected to be completed within 15 months and applied modern technologies of Europe,Japan, America to produce good products.

Some photos of the groundbreaking ceremony